Project Update: JUMP

Work continues on Jack’s Urban Meeting Place's underground garage. It should be almost completed by the end of the year, though it won't be finished until the facility opens in the summer of 2014. The $70 million downtown Boise project had 60 construction workers on site at the start of November. The project, led by ...