Boise Air Terminal Garage Expansion McAlvain Construction Location: Boise Owner: City of Boise Architect: Hummel Architects Completion: November 2013 Slab-on-grade work has started and is scheduled to be complete in April. Deck forms have arrived, and first-level shoring and beam forming has begun. The first post-tension deck placement is scheduled for late April.   Meridian Commons Wright Brothers, The Building Company, Eagle Location: East River ...