IBR Staff//June 6, 2014//
Bishop Kelly High School East Classroom Wing Addition
CM Company, Inc.
Location: Franklin Road in Boise
8,147 square foot classroom wing addition.
Architects: Erstad Architects
Engineers: Aspen Engineers / AHJ Engineers / Musgrove Engineering / E2Co
Completion: August 2014
Boise State East Campus Green Field
McAlvain Design Build, Inc.
Location: Boise
Description: Demolition of the Applied Technologies building, rough grading, and utility installation.
Owner: State of Idaho Division of Public Works
Field Designer: DA Hogan
Work on the drainage trenches, root zone sand, and the underground electrical system is complete. Sod and fencing are being installed while sidewalks are being formed and placed.
Carl’s Jr. Meridian Overland
Radix Construction
Location: South Meridian Road in Meridian
Owner: Green Star Properties
New 2,430 square foot restaurant.
Architect: Erstad Architects
Engineers: KM Engineering
Completion: May 2014
The project is complete.
Christian Brothers Automotive
HC Company
Location: West McMillan Road in Meridian
Owner: CBA Corporation
Description: 5,000 square foot auto service facility.
Architect: Cortland Morgan Architects, Arlington, TX
Engineers: AEdefica Case Engineers, St. Louis, MO / P.E. Services, Inc., Dallas, TX
Completion: March 2014
This project is complete.
Eide Bailly TI
HC Company
Location: West Main Street in Boise
Description: 16,000 square foot office tenant improvement.
Architect: Lombard-Conrad Architects
Engineers: Design/Build
Completion: October 2014
Construction documents are being developed.
EnerNoc, Inc. TI
HC Company
Location: North Discovery Way in Boise
Description: 4,000 square foot office tenant improvement
Architect: Johnson Architects
Engineers: ECI, Inc.
Completion: May 2014
This project is complete.
Florida Tile TI
HC Company
Location: South Featherly Way in Boise
Description: 2,000 square foot office and showroom addition.
Architect: Lombard-Conrad Architects
Engineers: Design/Build
Completion: May 2014
This project is near complete.
G&G Investments Phase 1 Site improvements – Nampa
Radix Construction
Location: Old Midland and Karcher Road in Nampa
Owner: G&G Investments
Architect: Radix Construction / John Day
Engineer: T.O. Engineers
Completion: August 2014
The contractor has mobilized to the site and utility work has started.
Idaho Central Credit Union
CM Company, Inc.
Location: North 2nd East in Rexburg.
5,671 square foot wood frame structure.
Architects: LCA Architects
Engineers: Keller and Associates / Breckon Land Design / Call Engineering / Engineering Incorporated / Eidam and Associates
Completion: August 2014
Overhead rough-in of the mechanical and electrical systems has started, and framing activities have commenced. Roofing activities will start in the coming weeks.
Idaho Central Credit Union – Idaho Falls Hitt Road Branch
CM Company, Inc.
Location: North 25th East in Idaho Falls.
4,936 square foot wood frame structure.
Architects: LCA Architects
Engineers: Keller and Associates / Breckon Land Design / Call Engineering / Engineering Incorporated / Eidam and Associates
Completion: August 2014
Overhead rough-in of the mechanical and electrical systems has started and framing activities have commenced. Roofing activities will start in the coming weeks.
Idaho Sports Medicine Institute Remodel
CM Company, Inc.
Location: 1188 University Drive, Boise State campus
12,000 square foot phased remodel
Architects: Gile & Associates Architects
Engineers: Engineering Inc. / Farren Engineering
Completion: May 2014
Work on phase 3 of the 4 phase project has started. The scope includes improvements and new construction of office spaces, exam rooms, an exercise/weight room area, locker rooms, treatment rooms, physical therapy stations, reception and storage areas.
Juniper Restaurant TI
HC Company
Location: North Eighth St. in Boise
Description: 3,000 square foot restaurant tenant improvement.
Architect: ALC Architecture
Engineers: Tikker Engineering / DC Engineering
Completion: June 2014
Brick is being seal coated, window stops are being installed, and the ceiling is being repaired. A new electrical panel is being set for service.
Kendall Ford New Facility
McAlvain Construction, Inc.
Location: Meridian
Owner: Kendall Auto
Architect: Straightline Architects
The car wash underground utility installation is near complete, and the trench drains and building slab are being placed. Interior masonry walls will be constructed in June while additional site work continues.
Kendall Ford Remodel/Expansion
McAlvain Construction, Inc.
Location: Meridian
Owner: Kendall Auto
Architect: Straightline Architects
The roof for the expansion of the service garage to the south and to the east has been installed, and the demolition of the walls will occur in June. The showroom remodel is ongoing along with interior wall framing and MEP rough-in. Site work continues on the south and east sides of the site.
Le Peep Restaurant Meridian
Radix Construction
Location: Gateway Market Place Shops Suite 130 Meridian
Owner: Le Peep Meridian LLC
New 1,737 square foot restaurant tenant improvement.
Architect: Radix Construction/John Day
Engineers: Tikker
Completion: April 2014
This project is complete.
Les Bois Park Turf Club Remodel
McAlvain Construction, Inc.
Location: Boise
Owner: Les Bois Park Racing LLP
Architect: Hummel Architects
This project is complete.
Meridian High School Renovation – Phase 2B (Annex Classroom Bldg Addition) & Phase 3A (Classroom Building Renovation)
CM Company, Inc.
Location: Meridian, ID
Owner: Joint School District No. 2
Phased Renovation
Architect: Hummel Architects
Engineers: Musgrove Engineering / KM Engineering / Axiom PLLC
Completion: Spring 2015
Bid documents have been published for a May 6th 2014 bid date.
Meridian WWTP Fermentation & Odor Control
Contractors Northwest, Inc.
Location: 10 Mile & Ustick in Meridian.
Owner: City of Meridian
Demolition of an existing and installation of new clarifier as well as the associated equipment. Includes upgrades to control and mechanical rooms.
Engineers: Ch2mHill
Completion: June 2014
This project has been completed and all systems are tested. In the next two weeks the system will be brought online.
NCMC Decontamination Room
Layton Construction
Location: Highway 46 in Gooding
Owner: North Canyon Medical Center
Decontamination room upgrade.
Architect: Architectural NEXUS
Completion January 2015
Robertson Supply Warehouse
HC Company
Location: 6th Street North in Nampa
Description: 18,000 square foot concrete tilt-up warehouse building.
Architect: Larson Architects, P.A,
Engineers: Tealy’s Land Surveying / Structural Engineering Consultants / Musgrove Engineering
Completion: August 2014
The tilt panels have been set, the slab pour-back strips have been placed, and overhead door and storefront installation is progressing. Crews are working on soffit framing.
RSD Warehouse
Contractors Northwest, Inc.
Location: Emerald & Mitchell
Description: New 26,000 square foot concrete tilt-up warehouse.
Architect: Licia LeGrant
Completion: May 2014
This project has been completed and is going through final inspections with a certificate of occupancy expected on 6-2-14.
Simplot Batter Mixing Facility
Layton Construction
Location: Simplot Blvd. in Caldwell
Owner: Stellar Group Inc.
Earthwork, utilities, and foundations for a 18,000 square foot batter mixing facility and the addition of a 200 LF rail spur.
Architect: Stellar Group, Inc.
Completion: July 2014
The placement of the stem walls continues and backfill work has commenced. Structural steel erection has started.
Starbucks Twin Falls
Radix Construction
Location: Blue Lake and Bridge View
Owner: Starbucks Coffee Company
1,759 square foot ground up.
Architect: Freiheit and Ho
Engineers: Sterling Design and Associates
Completion: October 2014
Site grading and utility work have commenced.
Sur La Table TI
HC Company
Location: Village at Meridian
Description: 5,770 square foot retail space tenant improvement
Architect: DG Group Architecture
Engineers: Hallberg Engineering
Completion: July 2014
The contractor has mobilized to the site. Layout, saw cutting, and underground mechanical and electrical rough-in work has started.
United Heritage 2nd Building
CM Company, Inc.
Location: East United Heritage Ct. in Meridian
20,000 square foot structural steel / CMU frame structure.
Architects: BRS Architects
Engineers: Harvest Design / KM Engineering / Stapley Engineering / Tikker Engineering / & E2CO.
Completion: February 2015
West Boise YMCA Tenant Improvements
Wright Brothers, The Building Company
Location: Discovery Way in Boise
Owner: Treasure Valley YMCA
2,500 square foot building improvements.
Architect: Rudeen & Associates
Completion: June 2014
Construction activities continue in the main building structure.
Willowcreek Elementary School – Phase 3
CM Company, Inc.
Location: Meridian, Idaho
Owner: Joint School District No. 2
Addition of gymnasium, stage, kitchen and administration areas. Work includes shell only for future classroom space.
Architect: LKV Architects
Engineers: Musgrove Engineering / Breckon Land Design / E2CO / Robert Peters Engineering
Completion: July 2014
Zasio TI
HC Company
Location: West Front Street in Boise
Owner: Zasio Investments, LLC
Description: 5,660 square foot office tenant improvement.
Architect: Erstad Architects
Engineers: Musgrove Engineering
Completion: April 2014
This project is complete.
Aquent TI
HC Company
Location: Explorer Drive in Boise
Description: 2,247 square foot office tenant improvement project.
Architect: The Architects Office, PLLC
Engineers: Design/Build
Completion: April 2014
This project is complete.
Trademark Sign Company
HC Company
Location: West Royal Blvd in Boise
Description: 5,000 square foot building renovation and office/shop tenant improvement.
Architect: Erstad Architects
Engineers: Erikson Civil Engineering / Tamarack Grove Engineering
Completion: May 2014
This project is complete.